DecisionEdge’s CloudEVM is the first to deliver seamless integration from Empower for aerospace and defense companies and DOE labs

Empower Optimized Integration delivers large cost and schedule data sets faster and more accurately through intelligent automation.
Oct. 29, 2019

AUSTIN, Texas – DecisionEdge recently announced its CloudEVM is the first to provide seamless integration from Primavera P6 to Encore's analytical tool Empower for both the Department of Energy (DOE) laboratories and aerospace and defense companies supporting the Department of Defense (DoD). This enables labs and companies to automatically upload and export cost and schedule data resulting in faster and more accurate processing of data through intelligent automation.

CloudEVM is the first to provide the new DOE PARSII CSV export format at Los Alamos National Laboratory, Y-12 National Security Complex, and the Pantex Plant.

CloudEVM's Earned Value Management System provides seamless integration with Microsoft Office Project, Excel, ERP and accounting systems, as well as P6. For DoD applications, CloudEVM integrates data from P6 directly to Empower, and for DOE applications, it sends the data to the Project Assessment and Reporting System (PARS), and then to Empower.

For more information, please visit https://www.decisionedge.com/index.asp.